The project included:
- Hydraulic modelling of approx. 5km of Merri Creek to Melbourne Water requirements.
- Preparing detailed concept design for bridges at 4 No. locations including approach roads.
- Preparation of detailed risk-based cost estimates at the P50 and P90 level.